Safe Clearwater Avenue

Clearwater Avenue

Important Dates


Start Date: Ph 3 - March, 2017
End Date: Ph 3 Approximately August, 2017
Location: West Clearwater Avenue (locations listed below)
Cost: $1.2 million (100% grant funded)

Project Description 
Phase 3
Phase 3 will reconfigure the intersection at Union Street, including median treatments.  Median treatments on Clearwater Avenue between Columbia Center Boulevard and Colorado Street and between Huntington and US - 395 will also be constructed.

Status

Phase 3 Clearwater Avenue Intersection Improvements bid opening was held on Tuesday, February 7, 2017.  Allstar Construction Group, Inc. was the low bidder.  The City of Kennewick is scheduled to award the project to Allstar Construction Group, Inc. at the February 21st Council Meeting. 
  

Project Estimates


  • Phase 1 - $425,000 Study, which included Public Involvement, Access Management Plan, Design - Completed
  • Phase 2 - $495,000 Right-of-Way Acquisition, if necessary - Completed
  • Phase 3 - $1,200,000 Construction
  • Project Total - $2.12 million (100% grant funded)