2023 Bituminous Surface Treatment Seal Coat (P2305-23)

Project Description

This project includes the application of bituminous surface treatment (BST) seal coat of paved residential streets and arterial streets within the Kennewick City limits.  Work also includes, but is not necessarily limited to pavement patching of selected areas for BST streets, pre-project sweeping by City crews, traffic control, covering and uncovering of utilities, removal of plastic pavement markings, supply, placement and removal of temporary flexible raised pavement markers, fog seal of pavement patches, constructing a single course BST, post project sweeping, sweeping sidewalks as required to remove any debris that results rom the project, haul and disposal of picked up excess rock to a City-provided waste site, application of gof seal, paint striping, and preformed thermoplastic pavements markings. 

More Info

Start Date:
June 2023
Est. End Date:
July 2023
Funding Source:
Street Fund

Project Contacts:

City Project Engineer: Kevin Biersner, P.E., - (509) 585-4524

City Project Inspector: Dan Jacobsen - (509) 727-3690

Contractor: Tommer Construction Company - Jeff Tincher (509) 398-7991

Status

Notice to proceed has been issued for June 5, 2023

Last updated 5/25/2023