Sharron & Rainier Waterline Improvement (P2018-21)

Project Description

Install 1,300 LF of new 8-inch water line in Sharron St. and 3rd Ave. Install 2 new fire hydrants, and install 42 new service laterals to existing homes.

More Info

Start Date:
February 2022
Est. End Date:
Summer 2022
Funding Source:
Water Fund - Deficient Main Replacement

Project Contacts

City Project Engineer: Mohammad Jalalyar, P.E. - (509) 585-4430

City Project Inspector: Rene Lopez - (509) 727-3689

Contractor: Double J Excavating, Calvin Matson - (509) 627-2030

Status

Work is scheduled to begin on February 14th and be completed in July. The contractor will be working closely with homeowners who's driveway and property are being affected.

Click here to view the construction flyer!

Last updated: 2/7/22