Install 1,300 LF of new 8-inch water line in Sharron St. and 3rd Ave. Install 2 new fire hydrants, and install 42 new service laterals to existing homes.
More Info
Start Date:
February 2022
Est. End Date:
Summer 2022
Funding Source:
Water Fund - Deficient Main Replacement
Project Contacts
City Project Engineer: Mohammad Jalalyar, P.E. - (509) 585-4430
City Project Inspector: Rene Lopez - (509) 727-3689
Work is scheduled to begin on February 14th and be completed in July. The contractor will be working closely with homeowners who's driveway and property are being affected.