Canal Drive Sewer Line (P1936-21)

Project Description

Installation of a new 12-inch dia. sewer line down Canal Dr. from the US395 bridge approximately 600 LF eastward to replace failing concrete line on the south side of roadway. Emergency repairs were completed in December 2019, enabling this project to be designed under non-emergency conditions.

More Info

Start Date:
August 2021
Est. End Date:
September 2021
Funding Source:
General Sewer fund

Project Contacts

City Project Engineer: Caleb Shannon, P.E. - (509)585-4289

City Project Inspector: Rene Lopez - (509) 727-3689

Contractor: Sharpe & Preszler Construction - (509) 586-1138

Status

The contractor is scheduled to begin work in mid-August.

Last updated 8/4/2021