Quinault & Columbia Center Blvd Intersection (P2011)
Quinault & Columbia Center Blvd Intersection (P2011)
Project Description
Project will provide a 2nd left-turn (LT) lane for added turning capacity for eastbound traffic turning north onto Columbia Center Blvd. A 2nd through-lane will be provided for westbound traffic on Quinault Ave. The project will be constructing curb, gutter, retaining walls, sidewalk, ground sloping, asphalt overlay, landscaping and street signal improvements within the existing intersection.
More Info
Start Date:
Spring/Summer 2024
End Date:
Winter 2025
Funding Source:
Design & ROW: Grant through BFCOG & FHWA Construction: BFCOG and FHWA Funded
Status
Project is in the right-of-way acquisition phase and design phase. The advertisement for contractor bids tentative timeframe will be Spring 2024. For more information on the proposed scope of this project, please see the concept drawling linked below.