W. 14th Pl. Outfall & Misc. Storm Sites (P1931-19)

Project Description

This project includes, but is notlimited to, construction of the following: Installation, repair and abandonmentof storm drywells, connecting to existing storm lines, installing approximately230 lineal feet of 10 and 12-inch diameter storm line, installing approximately486 lineal feet of 18- inch diameter storm line, installing approximately 120lineal feet of 12- inch diameter slotted drain pipe within City of Kennewickright-of-way as identified in the Specifications, Contract Plans, and Contractdocuments.

Important Dates

Start Date:
January 20, 2020
Estimated End Date:
March 10, 2020 (weather permitting)
Funding Source:
Stormwater Utility Fund
Estimated Cost:
$266,889.83


P1931-19 contactsStatus

Work is scheduled to be completed the week of February 10th

Last updated 2/6/2020