Hildebrand & Ridgeline Looping (Zone 4) P1706

Important Dates

Start Date:April, 2019
End Date:July, 2019
Location:See Project Description
Estimated Cost$308,000


Project Description

The Contractor for this job is Big D's Construction.  This project includes, but is not limited to, construction of the following: Approximately 2,206 lineal feet of 12-inch diameter ductile iron water main from an existing 12-inch stub, south of the intersection of South Sherman Street and West 33rd Place, to an existing 12-inch stub, east of the intersection of Ridgeline Drive and S. Nelson Street including installation of valves and fittings in an existing roadway right-of-way.  Asphalt patching and gravel shoulder restoration work will consist of the removal and disposal of the existing asphalt, top course surface preparation, paving with new asphalt, placing and compacting 5/8-inch minus rock.

Status

Contract has been awarded awaiting start of construction.