2018 City-Wide Asphalt Restoration P1801

Important Dates:

Start Date:    Late July, 2018

End Date:     Mid October, 2018

Location:       See Description Below

Est. Cost:       $1,255,000

Project Description

The contractor for this project is Central Washington Asphalt. This project is for the improvement of a portion of the following streets: Columbia Center Blvd. (W. Quinault Ave. to SR240 ROW), S. Washington Street (E. 10th Ave. to E. 19th Ave.), and S. Quillan Street (W. 27th Ave. to W. 28th Ave.). There will also be work on portions of Keywaydin Drive and the parking lot of Fire Station #4 located at 2620 W. 27th Ave.. Work will involve lowering of existing utilities, planing (grinding) as called for on the plans, patching of miscellaneous failed areas, minor sewer line replacement, overlaying, pavement lane striping, cross walks, stop bars, signage, traffic control, pavement markings and other work.

Status

The preconstruction conference was held on July 17, 2018.  Construction to begin soon.