Metaline Avenue Widening (P1309-18)                                                                

Project Description

This project is for the reconstruction of W. Metaline Avenue from N. Kellogg Street to N. Edison Street. Improvements include adding curb, gutter and sidewalk, reconstructing the asphalt roadway, re-striping, adjusting of new utilities, installing new water and sewer line, utility work, storm system construction, street lighting, signage, pedestrian ramps, traffic control, and other work as required.  Premier Excavation is the contractor selected for this project.

Important Dates

Start Date:
June, 2018
Estimated End Date:
November, 2019
Location:
Metaline Avenue
Estimated Cost:
$2,000,000

Status

Paving of top lift is scheduled for May 24th. 

Last updated 5/13/19