Vista Field Water Line Improvements

Important Dates

Start Date:    August, 2018

End Date:     Late November

Location:       Vista Field

Est. Cost:      $ 1,451,000

Project Description

This project is for the replacement of an existing 8" A.C. waterline on both N. Colorado Street and N. Young Street with a new 12" D.I. waterline in anticipation of the Vista Field Development. A new PRV vault will also be included with this work.  Both N. Colorado Street and N. Young Street will receive an asphalt overlay.  

Status

C & E Trenching is the contractor for this project.  Construction is not set to begin until August of 2018.