Sidewalk Improvements

Important Dates

Start Date:
Summer, 2018
End Date:    
End of November, 2018
Location:    
South side of E. 1st Avenue between Fir Street & Date Street
Estimated Cost:
$150,000

          

Project Description

The City has obtained a Community Development Block Grant (CDBG) to complete sections of missing sidewalk on the south side of E. 1st Avenue between S. Fir Street and S. Date Street.  This project will also include a section of missing sidewalk on the east side of S. Dawes Street between W. 3rd Avenue and W. 4th Avenue.  

Status

The Contractor for this project is Ray Poland and Sons.  A missing section of sidewalk was replaced at 4th and the E side of Dawes Street.  A new sidewalk is being built on First Avenue between Date Street and Gum Street.  This should be completed end of November.