2017 Asphalt Pavement Restoration

paving
 

Important Dates

Start Date:  July, 2017
​End Date:    October, 2017
​Location:     Misc. locations throughout the city.
​Cost:           $1,500,000  

​Project Description


This project is for the HMA patching of failed pavement areas throughout the city. Work includes traffic control, pavement markings, utility adjustments, and other miscellaneous improvements.  This contract was awarded to Inland Asphalt Company.

 

Status


  (These dates are subject to change and the contractor will do their best to adhere to this time line) 
  
 
The week of September 18th and 25th
Sept. 18, 10th Avenue - East Bound
Sept. 19, 10 Avenue - West Bound
Sept. 20,  Southridge Blvd.
Sept. 21, Ridgeline Drive
Sept. 22, Alder Drive
Sept. 25, W. 10th between SR395 and Union (intersection of 10th and Union) (night patching from 8:00 p.m. to 6:00 a.m.)
Sept. 26, 4th and Union finish up
Sept. 27, intersection of 4th and Edison and 4th at CCB
Sept. 28,Kennewick Avenue between SR395 and Olympia
Sept. 29, 10th & Olympia intersection depending on progress.
    

List of Street Restorations

This is a link to the locations that will be covered in this contract.