2017 Asphalt Pavement Restoration

paving


Important Dates
​Start Date:  June, 2017
​End Date:    September, 2017
​Location:     Misc. locations throughout the city.
​Cost:           $1,700,000  

​Project Description

This project is for the HMA patching of failed pavement areas throughout the city. Work includes traffic control, pavement markings, utility adjustments, and other miscellaneous improvements.  


Status
Contract awarded to Inland Asphalt Company on May 16, 2017