Southridge Boulevard Extension

Important Dates


Start Date: January 30, 2017
End Date:   May, 2017
Location:    Southridge Boulevard
Cost:          $1,020,000

Project Description


This project is for the reconstruction of Southridge Boulevard, north from Christensen Road for approximately 2100’ to tie into the existing curbs south of the Southridge Boulevard and Ridgeline Drive roundabout. The project includes water, sewer, storm drainage, curb and gutter, sidewalk, streetlights and other miscellaneous improvements.

This project was awarded to POW Contracting, Inc. 

Status


Contractor breaking rock and pre-digging sewer and storm trenches.  The City met with Contractor on site to discuss sewer and irrigation pipe.  Also discussing traffic control plan on closing Brinkley to 41st. The Gas Company in on site to complete their 6" tieover at Brinkley.