Zone 5 Reservoir Transmission Main

Reservoir


  Location:        Sherman Street to Thompson Reservoir
  Cost:              $440,000

  
 

 Status - Complete


 This project constructed approximately 2,877 lineal feet of 18-inch diameter ductile iron water main from the future intersection of Sherman Street and W. 30
th Avenue to the City’s Thompson Hill Reservoir. The project included excavation and embankment for a future street, construction of a gravel access road, and other miscellaneous work.